Latest Building Update

WEEK’s 9 & 10 December 4th-December 17th
High Country Construction completed framing the exterior walls, they installed the plywood sheathing and covered them with an air barrier wrap. They also completed the footers and piers for the columns for the front canopy and they saw cut the concrete floors as required.
Kozel steel installed the steel beams for the roof structure, they did not install the columns for the front canopy as they are waiting for the saddles for the tops that hold the wood beams in place.
We received the roof trusses and a forklift to set them in place.
High Country construction started to frame the flat roof at the connecting link and circulation counter.